Bike Path Road Work
+3
Trailrunner
brigitte
cerebrozo
7 posters
Page 1 of 1
Bike Path Road Work
Some extracts from a recent newspaper report:
• Since work began two months ago seven vehicles have fallen into the ditches.
• The lack of safety markers, the absence of any government (traffic department) agents, and malfunctioning traffic lights have aggravated traffic problems in the area.
• The organization responsible for overseeing the project is the State of Jalisco SIOP Ministry of Infrastructure and Public Works.
• The project was supposed to be completed in December, but it could be until March when the work is completed.
Ciclovía Lack of Signage in Ajijic Affects Motorists
Laguna, Periodico Seminal - 11 Dec. 2019
http://semanariolaguna.com/47770/
• Since work began two months ago seven vehicles have fallen into the ditches.
• The lack of safety markers, the absence of any government (traffic department) agents, and malfunctioning traffic lights have aggravated traffic problems in the area.
• The organization responsible for overseeing the project is the State of Jalisco SIOP Ministry of Infrastructure and Public Works.
• The project was supposed to be completed in December, but it could be until March when the work is completed.
Ciclovía Lack of Signage in Ajijic Affects Motorists
Laguna, Periodico Seminal - 11 Dec. 2019
http://semanariolaguna.com/47770/
cerebrozo- Share Holder
- Posts : 129
Join date : 2017-06-18
Re: Bike Path Road Work
Nothing new..
Road work is always done during the dry season , therefore the high season
Public work always start late and is always inconvenient
Public work always goes over budget
and specifically for this one , it is dangerous and poorly marked..
No one will argue with that one..
Road work is always done during the dry season , therefore the high season
Public work always start late and is always inconvenient
Public work always goes over budget
and specifically for this one , it is dangerous and poorly marked..
No one will argue with that one..
brigitte- Share Holder
- Posts : 4318
Join date : 2011-12-02
Re: Bike Path Road Work
I came close to being vehicle #8 yesterday afternoon.
Trailrunner- Share Holder
- Posts : 8007
Join date : 2011-04-18
Re: Bike Path Road Work
Today while heading to the west side, I noticed stanchions have been placed through La Floresta in the middle of the "ditch". I believe these will be mountings for lights. Any idiot of a civil engineer knows that you put objects that can be used to kill people in an accident far back from the road, not right next to it where it will be easily hit and damage cars and bodies. The light stanchions thru Ajijic are back on the edge of the sidewalk. Idiots!!!!!!!!
Gamina- Share Holder
- Posts : 1037
Join date : 2011-05-05
Re: Bike Path Road Work
Well with all the new lighting they will at least be able to see what they are hitting.......
_________________
Vacation Rentals
https://casadecomo.mx/
Similar topics
» Road work in Riberas
» Current Road Work in Chapala Centro
» Little Bike Cop
» Bike Wanted
» Cool bike
» Current Road Work in Chapala Centro
» Little Bike Cop
» Bike Wanted
» Cool bike
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum